W-5706L - N.C. 27 / Old Stage Rd / Leslie Campbell Road and N.C. 27 at Sheriff Johnson Road
W-5706L - N.C. 27 / Old Stage Rd / Leslie Campbell Road and N.C. 27 at Sheriff Johnson Road
The North Carolina Department of Transportation proposes to construct a roundabout at the intersection of N.C. 27 / Old Stage Rd / Leslie Campbell Ave. and dead end Sheriff Johnson Rd at N.C. 27.
Vicinity Map:
Interactive Study Area Map:
Map is for informational purposes only and reflects the approximate boundaries of the area in which environmental studies for the project will be conducted.
Project Overview
The N.C. Department of Transportation proposes to construct a roundabout at the N.C. 27 / Old Stage Rd (S.R. 1006) / Leslie Campbell Ave (S.R. 2084) intersection. Pavement removal is proposed at the NC 27 / Sheriff Johnson Rd (SR 1516) intersection.
Public Involvement
Public Meetings
Due to Covid 19, NCDOT has suspended in-person meetings. Information will be provided to the public in a virtual format on this website. The public is encouraged to provide comments or share their thoughts regarding the proposed map below.
Comments may be submitted below, via email to OldStageRd-Harnett@PublicInput.com or by calling 512-580-8850 and entering project code 8739.
The comment period for this project closes on August 31, 2022.
Public Meeting Map:
Updated public meeting map Roundabout at Old Stage Rd / Leslie Campbell Ave intersection.
A video explaining how to read a public hearing or meeting map can be viewed below. The video contains information on colors used and symbology.
Roundabouts in North Carolina
Project Funding:
This project is listed as Project W-5706L in the N.C. Department of Transportation’s State Transportation Improvement Program (STIP) and is funded for $ 5.175 million.
Activity | Estimated Costs* |
Project Development & Design | $ 900,000 |
Property Acquisition & Utilities | $ 1,775,000 |
Construction Cost | $ 2,500,000 |
Total Cost | $ 5,175,000 |
Estimated costs are subject to change. Based on currently adopted NCDOT STIP.
Project Timeline:
Milestone | Date* |
Public Outreach | August 2022 |
Final Environmental Consultation | January 2023 |
Right-of-Way Acquisition Begins | September 2022 |
Construction Begins | April 2024 |
* Future dates subject to change.