Please join us for a virtual public meeting Wednesday, November 4, 2020 from 4-5pm with a presentation at 4:00pm. 

The meeting presentation and handout (both coming soon) explain the preferred alternative for the improving the intersection.  The purpose of the meeting is to explain the overall proposed project, present the preliminary roundabout design and potential impacts, discuss how traffic will be maintained during construction, the proposed detour route, answer your questions, and receive your input.  

Options to join the meeting:

1. Online - video will start in the blue box above on November 4 @ 4pm.

If you're having difficulty with the video or audio: 

  • ​Try going to a different website and coming back to this website (https://publicinput.com/B6067)

  • Reload/refresh this page (right-click to see those options)

  • Audio - Ensure the speakers on your device (computer, phone, tablet, etc.) are working

    • ​You can also phone in to listen 

  • If those options don't work, call Public Information Officer Rebecca Dangelo at 419-373-4428

2. Phone - 855-925-2801 code 8150

​Request to join the queue to talk live with the project team. 

  • ​Only available during the meeting

  • ​Press * (star) to hear the options if you're already on the line

Or leave a voicemail comment.

  • Can be done anytime

3. Text - N136 to 73224 to submit a question or comment.

Text the number and you will be prompted to share your question or comment.

 

Please let us know your questions and comments through Friday, December 4, 2020!  

Push "Continue" below for additional roundabout information and learn about the different ways to submit questions and comments!

Schedule

complete
complete
November 4, 2020

Virtual Public Meeting

complete
complete
December 4, 2020

Comment Period Closes

complete
complete
February 2021

Expected Environmental Document Approval

complete
complete
Spring - Summer 2021

Detailed Design Begins

planned
planned
Winter 2021 – Spring 2022

Right-of-way Acquisition 

planned
planned
Summer 2022

Construction