PROJECT UPDATES

 

05/06/2024 -  Meeting Follow-Up and Other Relevant Info

On February 15, 2024, Discovery Place, along with Rodgers Builders and representatives from Mecklenburg County, hosted an informal meeting for neighbors to provide updates on the new nature museum. At the meeting neighbors were invited to share their questions regarding the project.

Below are questions about building and construction that were submitted along with answers. 

 

Q: How will property maintenance be addressed on Sterling Road?

A: The project should not impact how the edge of the park is currently maintained. Removing debris, fallen leaves or limbs, and trimming back overgrown vegetation is a part of routine general maintenance.

 

Q: Once construction begins on the new parking lot, where will those who are working onsite park their vehicles?

A: There will be a shuttle to get workers to and from the job site to minimize the amount of onsite parking required. Construction of the parking lot will be phased to ensure there’s always space for shuttle parking.

 

Q: What are the operating/working hours on the construction site?

A: Working hours will be Monday – Friday, 9:00 a.m. - 5:00 p.m. with occasional Saturday work as needed. There will be some activities that go past 5:00 p.m., but all work will stop prior to the cut-off of 9:00 p.m., per the city’s noise ordinance.

 

In addition to construction-related questions, many questions received were about museum operations. At this stage of the project, the focus is on building and construction. The builders anticipate an 18-24 month construction timeline, and we will continue to provide updates along the way, especially as it pertains to major milestones. The following information * is being offered in response to operational questions submitted during the meeting:

  • Museum operating hours will be 7 days a week, 9:30 a.m. - 4:30 p.m.
  • Museum capacity is 845 indoors
  • Discovery Place will comply with all city ordinances that relate to alcohol use and noise on premises
  • Museum-specific programming and special events are under development
  • The cost of the project, as reported in January 2024, is $62.3 million
  • All required surveys and due diligence were conducted prior to building demolition and construction

 

*Note: operational procedures, including Museum operating dates and times, may vary throughout the year and according to programming. As we move into operational planning, we will address questions specific to operations. In addition, Discovery Place is in the early stages of forming a neighbor committee that will provide input and guide some of the operational questions. 

 

 

03/08/2024 -  Project Update and Other Relevant Info

 

Mecklenburg County and Discovery Place would like to provide community residents with an update on the progress for the new Discovery Place Nature facility in Freedom Park.

Site construction for Discovery Place Nature is anticipated to begin in early April 2024 with an anticipated construction completion and opening in Fall 2025.

 

Pre-construction activities are scheduled to begin this week (week of March 11) and include:

  • Relocation of the Japanese Maple tree. The tree will be stored on-site during construction and transplanted on-site as construction is completed.
  • Crews will be conducting preliminary utility work along Sterling Avenue as a requirement from Charlotte Water. There will be a temporary lane closure on Sterling Road to allow crews to access a nearby manhole.

Discovery Place Nature- from Bridge

Discovery Place Nature- view from Freedom Park bridge over Little Sugar Creek

Discovery Place Nature- Floor Plan

Discovery Place Nature- Floor Plan

 

Discovery Place Nature- Saplings

Discovery Place Nature- Sapling (for visitors age 6 and younger)

Discovery Place Nature- Site Plan

Discovery Place Nature- Site Plan

Question title

Do you have any comments or questions about the project?

Question title

* Would you like to provide your contact information for future project updates?