Project Overview

 

We are adding two more travel lanes on U.S. Highway 189 (US-189) between Wallsburg and Charleston to reduce congestion and increase safety for drivers. This is the last stretch of US-189 in this area with only one lane each way. When finished, US-189 will have two travel lanes in each direction from Provo to Heber City.

The main focus of the project is building the new travel lanes into the eastern hillside as a separate and elevated road, known as a split highway, similar to a section of US-189 in Provo Canyon. An example of what the split highway could look like when finished is shown below.

Other key features being built with this project include:

  • New traffic signal at the intersection of US-189 and SR-113

  • Improved access and parking at the Island Beach Day Use Area, including longer acceleration and deceleration lanes and a new parking lot

  • Better sight lines through the curved section along US-189

  • New wildlife fencing to protect drivers and animals

Construction started in October 2025 and is expected to wrap up in fall 2027. 

 

 

Schedule* 

Full closures of US-189 will take place in both directions to allow crews time to safely complete necessary controlled blasting and hillside excavation:

  • Thursday, Dec. 18, between 10 and 10:35 a.m. - Full closure. Delays up to 50 minutes. 
  • Saturday, Dec. 20, through early Sunday, Dec. 21, 10 p.m. to 4 a.m.  - Full closure. Six hours with no access. 
  • Sunday, Dec. 21, from 4 to 9 a.m. - one-way alternating traffic with flaggers is possible for cleanup and fence repair work.

*Schedules are subject to change due to weather conditions and material availability

Contact Information

To contact the public information team with questions or concerns:

Stay Informed

To receive email updates, please fill out the form at the very end of the Impacts & Updates tab or email* the public information team at HeberValleyProjects@utah.gov and type "Updates" in the subject line.

*You are signing up for updates from all Heber Valley projects.

 

live
live
Active Construction

Construction New Northbound Lanes (fall 2025 to summer 2026)

  • Rockfall protection fencing installed (fall 2025)
  • Blasting and hillside excavation work (winter 2025 through summer 2026)
  • Paving (summer 2026)
  • Wildlife fencing installation (summer 2026)

Island Beach Area Undercrossing

  • The Lake House Restaurant at Deer Creek is open during construction

  • Traffic shifted onto temporary bypass lanes (fall 2025)

  • Construction of future parking lot (fall 2025 to summer 2026)

  • Construction of future undercrossing (fall 2025 to summer 2026)

planned
planned
Upcoming Construction

Southbound Lanes Reconstruction

  • Shift all traffic to new northbound lanes (fall 2026)
  • Better sight lines through curved sections of US-189 (fall 2026 to spring 2027)
  • Replace pavement (spring 2027)
  • Improve access and parking at Island Beach Day Use Area, including longer acceleration and deceleration lanes (spring to summer 2027)

Traffic Signal at Intersection of SR-113 & US-189

  • Install new traffic signal and intersection modifications (2026)

complete
complete
Project Milestones

  • Advertise project and select contractor (summer 2025)

  • Design project and develop construction plans (fall 2021 to spring 2025

  • Analyze environmental resources and compile the environmental document (fall 2021 to spring 2024)

  • Hold public hearing and comment period (spring 2024)