SR-111 Bridge Removals
SR-111 Bridge Removals
This safety improvement project includes removing the railroad bridges on S.R. 111 at 5500 S. and 7600 S, eliminating choke points and improving the shoulders.
What to Expect Overall
- Short-term travel delays
- Road closures and alternate routes
- Speed limit reductions in work zones
- Noise, dust, and vibration
- Lane closures with temporary traffic signals
- 12 ft. lane width restrictions
- Progress updates sent weekly, or as needed by email
- Restricted pedestrian access
Work will take place Monday through Friday, 6 a.m. to 8 p.m. with occasional nights and weekends. Plan ahead for possible travel dealys and use alternate routes when possible.
For your safety and the safety of others, stay alert and be aware of construction workers and equipment near travel lanes. Exercise caution and be prepared to stop for the tempoary traffic signals. Pedestrian access in work zone areas is restricted.
Current Update
|
7600 South Bridge Area
Soil nail wall activities are progressing, though moving slowly due to material shortages. We anticipate this work will continue for several more weeks. Crews are also working on the storm drains in this area, and traffic remains shifted onto temporary asphalt on the west side of the road. Construction activities are taking place during daytime hours, including weekends. Continue to expect noise, dust and vibration.
Please be aware of haul trucks entering and exiting the roadway and do not follow trucks into the work zone. Changing lane configurations, lane closures and reduced speeds will continue.
*Construction activity is weather, materials and equipment-dependent and subject to change.
Bridge Demolition Time Lapse Video
Schedule
March 21, 2022: Contruction Begins
Late Summer 2022: Construction Ends
*Construction activity is weather, materials, and equipment-dependent and subject to change.