Construction Update | Dec. 11, 2025 

 

I-15 Northbound – Reduced Travel Lanes

Crews are continuing work on the I-15 median structure to complete trenching just north of the I-15 Exit 338. I-15 northbound will have reduced travel lanes on Friday, Dec. 12 from 7 p.m. to 5 a.m. Drivers should plan ahead and expect intermittent delays during this work. 

 

Did you know? 

Trenching on I-15 allows crews to access and upgrade underground drainage and utility systems that help protect the roadway from flooding and long-term wear. Once the work is complete, the trench is backfilled and compacted in layers to ensure a smooth, durable road surface for drivers. 

 

16391_5600 South (SR-97) I-15 both directions SPUI construction

I-15 mainline work at 5600 South(SR-97) facing northwest.

 

5600 South – Overnight I-15 Southbound Ramp Shift

Beginning Friday, Dec. 12 at 7 p.m., crews will shift traffic to the west to continue construction on the SPUI (Single-Point Urban Interchange) interchange.

 

A SPUI is a special kind of highway interchange where all left turns are controlled from one traffic signal, making it look like a giant "X" and helping lots of cars move more efficiently through tight areas. Drivers should expect minimal to intermediate delays during this work. 

 

16391_5600 South - traffic sits under I-15 at SR-97)

Along 5600 South near I-15 mainline facing east.

 


Upcoming and Ongoing Activities

 

5600 South – Intermediate Lane Closures

Through the winter months, crews will implement occasional intermediate lane closures along 5600 South in both directions to accommodate finalizing flatwork (curb, gutter, sidewalk) between 2700 West and 3500 West. Crews will maintain one lane in each direction. Drivers should plan for slower traffic and delays during peak commute hours.

 

6000 South – Drainage Activities 

Crews recently began irrigation and storm drain work on the north side of of 6000 South near 2050 West, including cleanup around the pond. During this work, crews encountered an unknown utility line, which has delayed the remaining work for a few weeks. 

 

Flagging operations will be in place through mid-December. Drivers are encouraged to plan ahead and expect light delays. The road and business access will remain open to traffic, and the area will be plated each evening for safe travel.

 

16391_5600 South - 6000 South and 1900 West near 2050 W intersection facing west.

6000 South and 1900 West near 2050 W intersection facing west.

16391_5600 South - 5600 South aerial - from 2700 W to 3500 W

 

 

5600 South (SR-97) and 3500 West corridor facing east.

 

 

Freeway Park Dr. and Riverdale Rd. 

Crews are finishing flatwork along Freeway Park Dr. and completing installation of concrete barrier between Riverdale Rd. (Exit 338A) and Freeway Park Dr. this week. The Riverdale exit will remain open throughout this work. Drivers should expect minimal delays along Freeway Park Dr. 

 

16391_5600 South - Freeway Park Dr. Concrete Barrier Installation Crew

Concrete barrier installation work along Freeway Park Dr facing south.

16391_5600 South - Freeway Park Dr. Concrete Barrier Installation Warming Blankets

Concrete barrier installation along Freeway Park Dr facing south.


Pedestrian Safe Walking Routes

Safe walking routes were updated to include the activated HAWK (High-Intensity Activated crossWalk) light at 2100 West along 5600 South. Drivers: Slow down and be aware of the designated safe walking routes along 5600 South. Stay alert, watch for students and pedestrians in the area.

 

Pedestrian Safety

Prioritize pedestrian safety while navigating through our work zones. Here are some tips to keep in mind:

  • Stay Alert – always be aware of your surroundings. Look out for construction signs, workers, and potential hazards
  • Use Designated Pathways – these paths are designated to keep you safe from construction activities
  • Avoid Distractions – Refrain from using your phone or wearing headphones while walking through construction areas
  • Wear Visible Clothing – Wear bright or reflective clothing, this can help ensure your seen by workers and drivers

 

Let's work together to keep everyone safe!

16391_5600 South - Safe Routes Updated_English

 

16391_5600 South - Safe Routes Updated_Spanish

 


Know Before You Go! Download the UDOT Traffic App Today!
The UDOT Traffic app provides commuters and travelers with mobile access to information for the State of Utah roadways. 

The available information includes:

  • Emergency and incident notifications
  • Construction alerts
  • Anticipated delays and lane closures
  • Road conditions
  • Travelwise alerts
  • A zoomable, scrollable map-based display


*download available for iPhone and Android devices

Learn more about Travelwise Tips here.

Contact Us

Join our mailing list! Email us at 5600south@utah.gov to receive updates about the project.

The project team is here to help. Please call or email with any questions or comments.

Hotline: 385-383-6576

Email: 5600south@utah.gov 

 

*Construction schedules are subject to change due to weather, utility, material and equipment delays.

 

Project impacts to travel can be found on the UDOT Traffic Website, www.udot.utah.gov/traffic or by downloading the UDOT Traffic app. 

 

Driver Safety: Please prioritize safety while driving through the construction zones.

  • Slow down and maintain a safe following distance
  • Obey speed limits and follow posted signage
  • Be alert for crew members and equipment
  • Avoid distractions and be prepared for detours and lane changes
  • Drive patiently and cautiously to ensure everyone's safety on the road

Schedule 

complete
complete
Right-of-Way Acquisition (2022-2025)

complete
complete
Final Design (Winter 2025)

live
live
Construction Began (Summer 2023)

Work Days: Monday - Friday, 7 a.m. - 5 p.m.

What to Expect:

  • Daytime work
    • Occasional night and weekend work
      • (7 p.m.-7 a.m.)
  • Heavy equipment, support vehicles, and crew members
  • Temporary access restrictions
  • Ocassional lane shifts and closures 
  • Alternate routes 
  • Increased noise, dust and vibration

planned
planned
Project Completion (Fall 2026)