Project Overview

N.C. Department of Transportation proposes to construct a roundabout at N.C. 11 and Old Lake Road intersection.

Project Highlights

The project proposes to construct a roundabout in place of the four-way stop-sign controlled intersection at N.C. 11 and Old Lake Road.

Traffic will be detoured onto existing roadways during construction of the roundabout.  The off-site detour north of the project follows portions of Old Lake Road, Woodyard Road, and N.C. 87.  The off-site detour south of the project follows portions of U.S. 74/U.S. 76, N.C. 87, Old Lake Road, and Woodyard Road. 

Project History

In late 2019 NCDOT conducted a crash analysis to evaluate safety conditions at the N.C. 11 and Old Lake Road intersection.  From October 2014 to September 2019, 18 crashes occurred, including one fatal crash and 13 injury crashes.  Most of the crashes resulted from vehicles on Old Lake Road failing to yield to vehicles traveling on N.C. 11. Based on the results, STIP Project W-5806A was funded as a safety project.  In June 2021 the intersection was changed to a four-way stop-sign controlled condition as an interim safety measure to reduce crashes.  The proposed roundabout is recommended as the ultimate solution to continue to reduce crashes, while also providing better traffic mobility.  The project is currently in the development, environmental, and engineering phase.  In June 2022, after reviewing preliminary designs, engineering studies, and public comments, NCDOT decided to delay the project delivery schedule two years to perform further traffic evaluation. Right-of-way acquisition is currently scheduled to begin in Spring 2024 and construction is currently scheduled to begin in Spring 2025.

Public Involvement

Information was provided to the public in a virtual format on this website. The public was encouraged to provide comments or share their thoughts regarding the proposed map below during the public comment period from February 28, 2022 through March 15, 2022

 

Comments were submitted via email to NC11-OldLakeRd-Columbus@PublicInput.com or by calling 512-580-8850 and entering project code 4349.

Comments and questions received during the comment period pertained to the following themes and concerns:

•     Ability of tractor trailers, logging trucks, and large farm equipment to travel through the roundabout.

•     Consideration of a traffic signal or other options for the intersection.

•     Education for drivers traveling through a roundabout.

•     Concern for impacts to properties and community residents.

•     Project cost and funding concerns.

•     Re-study of safety conditions after the four-way stop condition was added.
 

 

Public Meeting Map:

 

Proposed preliminary design map of Roundabout at N.C. 11 and Old Lake Road

 

A video explaining how to read a public hearing or meeting map can be viewed here. The video contains information on colors used and symbology.

 

 

Roundabouts in North Carolina

 

Project Funding:

 

 Activity

 Funded costs Costs*

  Property Acquisition

$     85,000

  Construction Cost

 $ 1,342,000

  Total Cost

 $ 1,427,000

*Funded costs costs are subject to change. Based on currently adopted NCDOT STIP.

Project Timeline:

 

Milestone

    Date*

Public Outreach

March 2022

Final Environmental Document 

March 2022 

Right-of-Way Acquisition Begins

May 2024

Construction Begins

May 2025

* Future dates subject to change. 

Question title

Would you like to be added to the project email list?

Question title

Do you have any comments or questions regarding the proposed project?

Closed to responses

PROJECT CONTACT INFORMATION 

John Gauthier

Division Project Manager

NCDOT Highway Division 6

PO Box 1150

Fayetteville, NC  28302

PROJECT CONTACT INFORMATION 

Mark Reep, PE

Consultant Project Engineer

Whitman, Requardt & Associates, LLP

1201 Edwards Mill Road Suite 320

Raleigh, NC  27607

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish