What is the Project?

This project will widen and resurface South Gilmore Road between Flaig Drive and Resor Road to provide two travel lanes in each direction, and a center median/turn lane. The roadway will be widened through the intersection with Resor Road to eliminate the existing southbound merge that occurs to the north. The existing traffic signal infrastructure will be upgraded at the intersection, and signal timing will be optimized. New sidewalks will be provided with the project; these will be from Flaig Drive to Planet Drive on the west and from Mack Road to Resor Road on the east. Minor utility relocations will be required to accommodate the proposed improvements. Temporary easements are anticipated from approximately 17 parcels and permanent right-of-way is anticipated from approximately 2 parcels.

 

On the next few pages the virtual public meeting will begin. If you are accessing this site on a mobile device you will need to scroll across the tabs to see all content. You'll be able to revisit the virtual public meeting and provide comments until May 16, 2022. The comment period will end on May 16, 2022 but the website will remain available after that date until the final plans are complete. If you have any difficulties in viewing the materials presented please contact Nicholas Dill, City Engineer, at 513-867-4221, or NDill@fairfield-city.org.

planned
planned
Final Right-Of-Way Plans Approved

September 2022

planned
planned
Right-of-Way Acquisition

November 2022 thru August 2023

planned
planned
Final Drawings and Specifications Complete

September 2023

planned
planned
Sale of Project

January 2024

planned
planned
Anticipated Construction Start

March 2024

planned
planned
Anticipated Construction End

Fall 2024