Project Activities

Utility work at 1300 North

 

Road Closures:

 

 

  • 550 North on the west side at 2000 West is now open but the east side of the intersection will remain closed while crews continue to install wet utilities (sewer, water, secondary water, storm drain) under the road. Pedestrian access will be maintained.
  • 1300 North is still closed at 2000 West on both sides due to utility conflicts. 1300 North will open as early as Monday, February 5. Detour routes are in place (see map here) until 1300 North is opened. Pedestrian access will be maintained. Once this work is completed the road will be patched with asphalt until new concrete is placed later this year.
  • Beginning as early as Monday, February 5, crews will close 800 North at 2000 West as they continue installing utilities under the road. This closure will be in place for approximately three weeks. A detour route will be in place (see map below). 1300 North and the east side of 550 North will be open before the 800 North closure is in place.
  • 750 North is closed for approximately two weeks as crews install utilities under the road.

Night Work:

 

  • Crews continue to work on sewer lateral, culinary water, and storm drain connections between 470 North and 550 North through this week. This work is taking place nightly from 7 p.m. to 6 a.m. Area residents can expect an increase in nighttime-related noise and light. To facilitate the installation of these utilities, crews will reduce 2000 West through the area to one lane controlled by flaggers. Motorists are advised to slow down and pay attention.
  • Beginning as early as next Monday, February 5, crews will begin work on the new sewer main. This work will require crews to one-way flag 2000 West to make enough room for crews and vehicles to work. This work will take place nightly from 7 p.m. to 6 a.m. for approximately six weeks and will begin at 470 North and work north to 800 North.

 

Ongoing Utility Installation: Utility work has begun north of 1300 North as work has progressed faster than anticipated and crews took advantage of the weather.

 

  • Gas line from 1300 North to 1800 North
  • Culinary waterline from 800 North to 1300 North and 550 North crossing
  • Storm drain through the 1300 North intersection headed north and the 550 North crossing
  • Secondary water from 550 North to 1300 North
  • Power pole relocation is ongoing from 470 North to 800 North
  • Homeowners can expect intermittent access limitations at their properties as this utility work occurs.

 

 

Drivers can expect shifting traffic patterns. Please reduce your speed through the work zone.

 

 

Contact the Public Involvement Team

Phone |888-556-0232

Email | 2000west@utah.gov

Project Schedule

complete
complete
Environmental Re-Evaluation

Fall 2020 - Summer 2021

complete
complete
Project Design

Summer 2021 - Summer 2022

complete
complete
Right-of-Way Acquisition

Summer 2021 - Summer 2023

live
live
Begin Construction

October 16, 2023