Project Overview

Why are we holding a virtual public meeting?

Due to the current health situation, The City of Middletown and ODOT are hosting virtual public involvement meetings to engage and seek input from the public about the reconstruction of Central Avenue.

Internet Access Difficulties

A transcript of videos presented here and a printout of exhibits will be provided to anyone who has issues accessing the virtual public meeting.  Please send a transcript request to Jeff Heimann for the BUT-CR609-0.00 PID 109468 virtual public meeting at one of the following contact methods:

Strand Associates, Inc.

Attn: Jeff Heimann

615 Elsinore Place, Suite 320
Cincinnati, OH 45202

Telephone Number: 513-861-5600 ext. 5223

E-mail: jeff.heimann@strand.com

Question title

* In place of a meeting sign-in sheet, please let us know you're here by filling in your contact information below.

Question title

Before you begin, please take a moment to let us know how you received notice of this virtual public meeting.

Postal Mail
83%
Other
17%
Word of Mouth
0%
Social Media
0%
Email
0%
Notice/Ad in Newspaper
0%
Closed to responses | 6 Responses

Schedule

complete
complete
October 16, 2020

Virtual Public Meeting/Public Comment Period Begins

complete
complete
November 16, 2020

Public Meeting Comment Period Closes

complete
complete
August 2021

Design complete

complete
complete
October 2021

Construction bids received 

planned
planned
March 2022-November 2022

Estimated Construction