Kasigluk Operations Summary

4/01/26

  • Mass-X crew working on removing snow and boardwalk demo. 

3/31/26

  • Mass-X crew working on removing snow and boardwalk demo. 

3/29/26

  • Mass-X crew completed snow removal and demo. Currently taking inventory of their construction materials and trying to recover the delivered lumber from under snowdrifts - crews intend to begin driving helicals by next week. 

3/28/26

  • Mass-X crew completed snow removal and demo. Currently taking inventory of their construction materials and trying to recover the delivered lumber from under snowdrifts - crews intend to begin driving helicals by next week. 

3/27/26

  • Mass X got a skid steer hauled over to Kasigluk to finish the last portion of snow removal from around the damaged sections of boardwalk - crews intend to begin driving helicals by next week. 

3/25/26

  • Mass-X got a skid steer hauled over to Kasigluk to finish the last portion of snow removal from around the damaged sections of boardwalk - crews intend to begin driving helicals by next week. 

3/23/26

  • Mass-X continued to dig out boardwalk repair locations and boardwalk materials that have been drifted over. 

3/21/26

  • Mass-X continued to dig out boardwalk repair locations and boardwalk materials that have been drifted over. 

3/20/26

  • Mass-X continued to dig out boardwalk repair locations and boardwalk materials that have been drifted over. 

3/17/26

  • Loader is back up and operational. Continuing to remove snow. 

3/14/26

  • Loader for snow removal is down, and cold weather is hampering repairs. 

3/09/26

  • Loader back up and operational, continuing with snow removal. 

3/02/26

  • Loader for snow removal is currently down and cold weather has hampered repairs. 

3/28/26