10/19/2025 Boardroad and Roadway Repairs Initiated

Nightmute Operations Summary

4/01/26

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #N03: Removed residential trash and debris. 
  • #N08: Started interior sheeting (35% complete). Installed ice and water shield plus roof tin (100% complete). 
  • #N10: Finished porch roof (100% complete). 
  • #N33: Lifted home 5" (50% complete). 
  • #N57: Electrical rough-in (90% complete). 
  • Total of nine team members onsite.