Project Overview

The I-15 Nephi Bridges Project is Complete!

Thank you for your patience and cooperation while traveling through Nephi this past year as construction crews completed work to preserve our state’s freeway infrastructure.

This project covered over 19 miles and accomplished:

  • Replacement of two bridge decks and the related roadway transitions.

  • Repair of seven bridge structures.

  • Rehabilitation of 80 lane miles of pavement, which included the replacement of 13,500 square yards of concrete.

All travel lanes and entrance and exit ramps are open.


 

Project Photos

I-15 near exit 222 looking northbound at the railroad bridges and the Nephi mainstreet bridges. 


 

I-15 near exit 225 looking northbound at the Nephi 100 North bridges. 


 

I-15 near just north of exit 225 looking northbound at the Nephi 700 North bridges

Schedule

complete
complete
Design: Spring 2021 - Fall 2022

complete
complete
Construction: Summer 2023 - Summer 2024