The Bloomingdale Avenue Drainage Improvements Project includes the acquisition of the land associated with 2801 Bloomingdale Ave. in Valrico. This land may provide additional capacity to attenuate stormwater runoff volume. The excavation of this parcel will reduce flooding on adjacent properties and Bloomingdale Avenue.

QUICK FACTS (CIP# 46145098)  

 

Location: Palm River, District 1

 

Project Type: Stormwater and Water Quality Improvements  

 

Current Project Phase: Design
 

Project Objectives:

  • Excavation of this parcel will reduce flooding on adjacent properties and Bloomingdale Avenue. 

 

Estimated Project Schedule:

Project Development (Planning) Completion -  N/A

Design/Land Acquisition Completion - Late 2026 

Procurement Completion - N/A 

Construction Completion - Late 2027

 

Project Cost Estimate:

Total: $990,000

Planning: $0

Design and Land: $640,000

Construction: $350,000  

 

Note: The cost and schedule data shown here are the County's current best estimates and are subject to change.