Project Overview

The Utah Department of Transportation (UDOT) is widening US-89 (State Street) to a 7-lane section from 220 South in Pleasant Grove to 500 East in American Fork in two phases. The project will alleviate traffic by widening the road to three lanes in each direction to match existing sections on either end; upgrade signals at 500 East, 700 East, North County Boulevard, 1300 West, and Pleasant Grove Boulevard; add new curb, gutter, and sidewalk on the south side, add new storm drain, and add new/upgrade pedestrian ramps.

 

Phase 1:

The following intersections will be widened to help reduce congestion:

  • 500 East at State Street in American Fork in 2025. 
  • Pleasant Grove Boulevard at State Street in 2025. 
  • 1650 West to 1300 West in 2025
  • State Street will receive a new pavement layer between the intersections.
  • Construction in this phase is anticipated to finish in October 2025.

 

Phase 2:

  • Phase 2 from 1650 West in Pleasant Grove to 600 East in American Fork is currenlty in design with construction planned in 2026. 1300 West will be widened during phase 2.

Project Schedule

live
live
State Street/500 East Intersection

Project Activities*:

  • Thursday night, November 13, beginning at 10 p.m. crews will be working on the signals at 500 East and Pleasant Grove Boulevard. This work will require single lane closures where work is taking place and motorists are advised to slow down and expect minor delays.
  • The final application of paint striping has been applied along the entire project corridor.
  • Waterline installation continues east of the 500 East intersection on the north side through next week. Shoulder closures will be used during this work.
  • Project wide cleanup will be ongoing through November as the project nears the finish.

*Dates are subject to change due to weather, equipment availability or other circumstances

 

live
live
State Street and Pleasant Grove Boulevard Intersection

Construction began February 27, 2024

complete
complete

  • State Street Pavement Rehabilitation 

  • Pleasant Grove and North County Boulevard Intersection

  • SR-74 (100 East) Deep Curb Replacement

Stay Informed: Sign up for email updates to stay informed about impacts that could affect your travel at afpgimprovements@utah.gov. Or, reach out to the team for questions or concerns at 888-556-0232.