East Charlotte Park Vision Plan:

East Charlotte Park Vision 2024

For a copy of the full East Charlotte Park Master Plan Report, go to the Documents Section below. 

Project Timeline

complete
complete

Schematic Design

July 2025 - February 2026

  • Community Engagement:  December 2025

complete
complete

Design Development

February 2026 - June 2026

live
live

Phase 1 Development

  • Construction Documents:  July 2026 - January 2027
  • Permitting:  Fall 2026 - Winter 2026/27
  • Bidding:  Spring 2027
  • Construction:  Summer 2027 - Fall 2027

planned
planned

Phase 2 Development

  • CIP Funding FY 2030
  • Construction Documents:  Summer 2029 - Spring 2030
  • Permitting:  Spring 2030
  • Bidding:  Fall 2030
  • Construction:  Winter 2030 - Spring 2031