Atmautluak: DOT&PF Emergency Repair Work
Atmautluak: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Atmautluak Operations Summary
4/01/26
- Mass-X continued on boardwalks on the south side of town, cutting piles to elevation and constructing boardwalks.
3/31/26
- Mass-X continued on boardwalks on the south side of town, cutting piles to elevation and constructing boardwalks.
3/30/26
- Mass-X continued on boardwalks on the south side of town, cutting piles to elevation and constructing boardwalks. Roughly 80 linear feet remaining.
3/29/26
- Mass-X continued on boardwalks on the south side of town, cutting piles to elevation and constructing boardwalks. Roughly 80 linear feet remaining.
3/28/26
- Mass-X continued on boardwalks on the south side of town, cutting piles to elevation and constructing boardwalks. Roughly 180 linear feet remaining.
3/27/26
- Continuing to work on installing helical piles and building boardwalk.
3/25/26
- Continuing to work on installing helical piles and building boardwalk.
3/24/26
- Continuing to install helical piles and building boardwalk. Ice road has been cleared of drifts to Atmautluak. Hog River will deliver the last bits of lumber needed to complete the boardwalk curbs.
3/23/26
- Continuing to install helical piles and building boardwalk. Ice road has been cleared of drifts to Atmautluak. Hog River will deliver the last bits of lumber needed to complete the boardwalk curbs.
3/22/26
- Mass X continued working on boardwalk on the south side of town. Crew continues to predrill.
3/21/26
- Boardwalk construction continues. Snow removal and boardwalk demo are complete for helical pre-drill and installation. Helical piles are currently being installed at an average of 16 piles a shift. They plan to continue installing boardwalk decking in Atmautluak while installing piles in Kasigluk.
3/20/26
- Boardwalk construction continues. Snow removal and boardwalk demo are complete for helical pre-drill and installation. Helical piles are currently being installed at an average of 16 piles a shift. They plan to continue installing boardwalk decking in Atmautluak while installing piles in Kasigluk.
3/17/26
- Boardwalk construction continues. Snow removal and boardwalk demo are complete for helical pre-drill and installation. Helical piles are currently being installed at an average of 16 piles a shift. They plan to continue installing boardwalk decking in Atmautluak while installing piles in Kasigluk.
3/16/26
- Mass-X working on south side of town predrilling and installing helical piles.
3/15/26
- Mass-X working on south side of town predrilling and installing helical piles.
3/10/26
- Mass-X finishing up vehicle crossing at fuel farm boardwalk - installing last sections of hand railing. Separate crew working on south side of town predrilling and installing helical piles.
3/09/26
- Mass-X working on south side of town predrilling and installing helical piles.
3/08/26
- Mass-X finishing up vehicle crossing at fuel farm boardwalk - installing last sections of hand railing. Separate crew worked on south side of town predrilling and installing helical piles.
3/05/26
- Mass-X finishing up vehicle crossing at fuel farm boardwalk - installing last sections of hand railing. Separate crew worked on south side of town predrilling and installing helical piles.
3/02/26
- Section to fuel farm is complete. Pre-drilling bit is currently down. Working on various equipment repairs due to cold weather.
3/29/26
3/28/26
3/23/26
3/22/26
3/17/26
3/08/26
3/06/26