City of Staunton – Richmond Avenue (Route 250) and Crossing Way Shared Use Path
City of Staunton – Richmond Avenue (Route 250) and Crossing Way Shared Use Path
This 0.45-mile project will improve safety and connectivity for pedestrians, and improve access to transit facilities for pedestrians and bicycles. The project will also enhance economic development by improving congestion, mobility and access to surrounding properties.
The project will construct an 8-foot-wide Shared-Use-Path along the south side of Richmond Avenue (Route 250) and along the east side of Crossing Way to the existing roundabout in the city of Staunton. The Shared Use Path will narrow to a 6-foot crossing over the CSX railway bridge. The corridor study selected the south side of Richmond Road to receive the shared-use path due to available right-of-way, proximity to Frontier Center businesses, and a wider deck on the eastbound railway bridge.
Concrete barrier and fencing along the right shoulder of the eastbound bridge will separate pedestrians and cyclists from traffic lanes. All crosswalks are proposed to be high visibility with accessible signals, push buttons, and pedestrian countdown signal heads at the signalized intersections with Frontier, Frontier Center Trail, and Crossing Way. Two-stage pedestrian crossings are proposed across Richmond Road.
The Richmond Avenue and Crossing Way shared-use path is Project 1 of the Richmond Road Multimodal Corridor Study conducted in 2009. The Staunton-Augusta-Waynesboro (SAWMPO) partnered with the City of Staunton, Augusta County and VDOT to identify strategies for improved multimodal connectivity, safety, and traffic operations.
In 2022 Richmond Avenue had an average traffic volume of 26,000 vehicles per day. By the design year of 2035 the estimated traffic volume is 34,000 vehicles per day.
In 2023 Crossing Way had an estimated traffic volume of 5,500 vehicles per day. By the design year of 2035 the estimated traffic volume is 11,200 vehicles per day.
The total estimated cost of this project is $5,113,818, which includes $387,844 for preliminary engineering, $879,804 for right of way and $3,846,170 for construction. This project received funding from Virginia’s SMART SCALE program for prioritizing transportation improvements.
Benefits
This project will improve pedestrian and bicycle connectivity along Richmond Avenue and Crossing Way, and access to transit facilities.
Public Outreach
A design public hearing is being held for this project:
- Wednesday, February 21, 2024, from 4 – 6 p.m.
- Location: Frontier Culture Museum (Dairy Barn Lecture Hall), 1290 Richmond Ave., Staunton, VA 24401
- The public comment period closes on March 2, 2024.
In the event of inclement weather, the meeting will be held Wednesday, February 28, 2024, at the same time and location.
Design Public Hearing Materials
Will be posted soon in the Documents & Materials tab below
Resources
Contact Information:
Aaron Warr, Project Manager
Aaron.Warr@VDOT.Virginia.gov
Phase: In Design
State Project Number: 0250-132-371, C501, P101, R201
Federal Project Number: STP-5132(169)
UPC: 119651
Lat/Long: 38.13183, -79.04037
Locality: City of Staunton, VDOT Staunton District